Time period
Object
Construction cost
Client
Services
2019-2016
>25 Mio
Hafenbogen GmbH & Co. KG
thermal construction physics, building and room acoustic, daylight simulation, construction noise and immission insulation, measurment of outside noise including aircraft noise, assessment of relevant exterior noise level
Client: |
Hafenbogen GmbH & Co. KG |
Cost: |
>25 Mio € |
Office building with canteen and bar lounge at the top floor.
|
thermal construction physics, building and room acoustic, daylight simulation, construction noise and immission insulation, measurment of outside noise including aircraft noise, assessment of relevant exterior noise level
|
2019 - 2017
10 Mio.
Lang & Cie. Real Estate AG
building physics, sound and thermal insulation, acoustics, immission insulation, construction and demolishing noise conception
Client: |
Lang & Cie. Real Estate AG |
Cost: |
10 Mio. € |
New construction of an office building with conference and examination rooms for the General Medical Council of the state Hessen.
|
building physics, sound and thermal insulation, acoustics, immission insulation, construction and demolishing noise conception
|
2018-2016
8 Mio
Lang & Cie. Real Estate AG
thermal builbing physics, room acoustics, day light calculation, thermal building simulation, construction noise and immission control concept
Client: |
Lang & Cie. Real Estate AG |
Cost: |
8 Mio € |
Office building with auditoria at the ground floor and terrace at the 6 th floor with an shared underground car park.
|
thermal builbing physics, room acoustics, day light calculation, thermal building simulation, construction noise and immission control concept
|
2018-2015
23 Mio.
Lang+Cie
noise insulation certificate, immission insulation for car park and ventilation system, room acoustics, LEED simulation, noise immission calculation for mechanical workshop, construction noise concept, daylight simulation for LEED
Client: |
Lang+Cie |
Cost: |
23 Mio. € |
New construction office building on LEED Goldlevel
|
noise insulation certificate, immission insulation for car park and ventilation system, room acoustics, LEED simulation, noise immission calculation for mechanical workshop, construction noise concept, daylight simulation for LEED
|
2017-2011
>25 Mio
OFB
thermal simulation, immission insulation cretificate, construction noise concept and construction noise measurment, ENEV-certificate, construction and room acoustics
Client: |
OFB |
Cost: |
>25 Mio € |
New construction of two office buildings, one residential building and one hotel, rehabilitation of a listed office building ( former Federal Audit Office), architecture KSP
|
thermal simulation, immission insulation cretificate, construction noise concept and construction noise measurment, ENEV-certificate, construction and room acoustics
|
2017-2000
7,5 Mio.
DeTe-Immobilien/Strabag Hr. Rockel
structural engineering HOAI 1-4, constructional fire protection, sound and thermal insulation, 3-D calculation of thermal bridges, sound measuring on the stock, calculation of the sound immission
Client: |
DeTe-Immobilien/Strabag Hr. Rockel |
Cost: |
7,5 Mio. € |
Internal and facade restructuration
|
structural engineering HOAI 1-4, constructional fire protection, sound and thermal insulation, 3-D calculation of thermal bridges, sound measuring on the stock, calculation of the sound immission
|
2017 - 2015
10Mio
Lang & Cie. GmbH
thermal insulation, noise control, acoustics, H&S, DGNB, energy concept, daylight calculation, thermal building simulation, immision control, construction noise concept
Client: |
Lang & Cie. GmbH |
Cost: |
10Mio € |
Office building with an adult education facility at the ground floor with underground car park.
|
thermal insulation, noise control, acoustics, H&S, DGNB, energy concept, daylight calculation, thermal building simulation, immision control, construction noise concept
|
2017 - 2015
Lang&Cie. GmbH
thermal and sound insulation, acoustic, immission insulation, construction noise, thermal building simulation for maintenance of the summer thermal insulation, SIGEKO
Client: |
Lang&Cie. GmbH |
Cost: |
€ |
Office building with underground car park
|
thermal and sound insulation, acoustic, immission insulation, construction noise, thermal building simulation for maintenance of the summer thermal insulation, SIGEKO
|
2017 - 2015
9 Mio.
Lang & Cie. GmbH
building physics, SiGe, thermal insulation, noise control, immission control, construction noise concept, room acoustics, Leed certification, building and daylight simulation, thermal comfort simulation
Client: |
Lang & Cie. GmbH |
Cost: |
9 Mio. € |
New construction of a hotel with underground car park
|
building physics, SiGe, thermal insulation, noise control, immission control, construction noise concept, room acoustics, Leed certification, building and daylight simulation, thermal comfort simulation
|
2015-2012
11 Mio.
Da-Di-Werk
structuraql engineering HOAI 1-6, thermal, sound and immission insulation calculation, room acoustics, temperatural calculation of existing basin
Client: |
Da-Di-Werk |
Cost: |
11 Mio. € |
|
structuraql engineering HOAI 1-6, thermal, sound and immission insulation calculation, room acoustics, temperatural calculation of existing basin
|
2015-2011
7,0 Mio.
Lang+Cie, Fr. Keilholz
structural engineering HOAI 1-6, fire protection and safety plan, temperaural calculation of ripped ceiling, sound insulation, EnEV, sound immission insulation, room acoustics, construction noise measurment , calculation of shading of the entrance foyer
Client: |
Lang+Cie, Fr. Keilholz |
Cost: |
7,0 Mio. € |
Facade lifting and retrofitting of office building
|
structural engineering HOAI 1-6, fire protection and safety plan, temperaural calculation of ripped ceiling, sound insulation, EnEV, sound immission insulation, room acoustics, construction noise measurment , calculation of shading of the entrance foyer
|
2014-2012
23 Mio.
Lang+Cie
sound insulation certificate, immission insulation certificate, room acoustics, room acoustics simulation plural Callcenter, noise control calculation, thermal insulation, simulation/analysis of building components at high temperaturs of an parking level
Client: |
Lang+Cie |
Cost: |
23 Mio. € |
New construction office building on LEED Goldlevel
|
sound insulation certificate, immission insulation certificate, room acoustics, room acoustics simulation plural Callcenter, noise control calculation, thermal insulation, simulation/analysis of building components at high temperaturs of an parking level
|
2014-2012
10 Mio.
Lang+Cie Hr. Holler
thermal insulation, noise control, room acoustics, DGNB
Client: |
Lang+Cie Hr. Holler |
Cost: |
10 Mio. € |
New construction of an office building head office
|
thermal insulation, noise control, room acoustics, DGNB
|
2014-2011
35 Mio.
Lang+Cie Hr. Geiger
Client: |
Lang+Cie Hr. Geiger |
Cost: |
35 Mio. € |
New construction passive house office and university building with lecture halls
|
|
2013-2012
15 Mio.
PM Architekten
Hr. Pischulti
Client: |
PM Architekten Hr. Pischulti |
Cost: |
15 Mio. € |
Planned facade and internal restructuration, new construction of an annex to an existing high-rise office building to achieve a zero-energy house
|
|
2013-2011
8 Mio.
Lang+Cie Hr. Holler
thermal insulation, noise control, DGNB Audit, room acoustics simulation, thermal building physics, sound immission calculation, sound measurement, H&S coordination
Client: |
Lang+Cie Hr. Holler |
Cost: |
8 Mio. € |
New construction office building as DGNB Silver level
|
thermal insulation, noise control, DGNB Audit, room acoustics simulation, thermal building physics, sound immission calculation, sound measurement, H&S coordination
|
2013-2011
15 Mio.
Lang+Cie Hr. Glatter
Thermal insulation, noise controll, DGNB Audit, room acoustics, room acoustics simulation, thermal simulation, daylight simulation, thermal building physics, sound immission calculation, sound measurement
Client: |
Lang+Cie Hr. Glatter |
Cost: |
15 Mio. € |
Restructuration office building Frankfurt as DGNB Gold level
|
Thermal insulation, noise controll, DGNB Audit, room acoustics, room acoustics simulation, thermal simulation, daylight simulation, thermal building physics, sound immission calculation, sound measurement
|
2013-2011
Hochbauamt Frankfurt Fr. Igel
Client: |
Hochbauamt Frankfurt Fr. Igel |
Cost: |
€ |
New construction of several passive house kinder gardens in buidling set technology
|
|
2013-2001
30 Mio.
OFB Hr. Hablowetz
structural engineering HOAI 1-4, EnEV 2002-2009, thermal construction physiks, sound insulation, room acoustics, concept of a passive house within an acquisition
Client: |
OFB Hr. Hablowetz |
Cost: |
30 Mio. € |
Planning of an office building
|
structural engineering HOAI 1-4, EnEV 2002-2009, thermal construction physiks, sound insulation, room acoustics, concept of a passive house within an acquisition
|
Client: |
|
Cost: |
€ |
New design of a call center
|
|
Client: |
|
Cost: |
€ |
New design of a call center
|
|
2011
EEG Offenbach Hr.Schindler
Client: |
EEG Offenbach Hr.Schindler |
Cost: |
€ |
New construction of a primary passive house school
|
|
2011
EEG Offenbach, Hr. Monath
Client: |
EEG Offenbach, Hr. Monath |
Cost: |
€ |
Refurbishment of a kindergarden
|
|
2010-2009
Hochbauamt Frankfurt am Main
Client: |
Hochbauamt Frankfurt am Main |
Cost: |
€ |
New construction of a school building
|
|
2010-2008
7 Mio.
OFB Hr. Berg
Client: |
OFB Hr. Berg |
Cost: |
7 Mio. € |
New constrcution of passive house office building
|
|
2010-2007
5 Mio.
OFB Hr. Bender
structural engineering HOAI 1-6, EnEV 2009, thermal construction physics, sound and immission insulation, fire protection and safety plan, calculation and simulation of the room acoustics
Client: |
OFB Hr. Bender |
Cost: |
5 Mio. € |
New construction and conversion of an office building for the Sparkaase- and Giroassociation in Frankfurt am Main.
|
structural engineering HOAI 1-6, EnEV 2009, thermal construction physics, sound and immission insulation, fire protection and safety plan, calculation and simulation of the room acoustics
|
2010
EEG Offenbach Hr.Monath
Client: |
EEG Offenbach Hr.Monath |
Cost: |
€ |
New construction of a passive house sport hall
|
|
Client: |
Main-Taunus-Kreis |
Cost: |
€ |
New construction school building and cafeteria as passivehouse
|
|
2008-2007
30 Mio.
Groß+Partner/OFB
Hr. Unger
constructural engineering HOAI 1-6, EnEv 2009, thermal construction physics, thermal simulation, sound insulation and room acoustics
Client: |
Groß+Partner/OFB Hr. Unger |
Cost: |
30 Mio. € |
New construction highrise building Werfthaus in Frankfurt former harbour area directly adjacent to the Main river with thermally activated concrete core cooling
|
constructural engineering HOAI 1-6, EnEv 2009, thermal construction physics, thermal simulation, sound insulation and room acoustics
|
2008-2007
3 Mio.
OFB Hr. Kunz
structural engineering HOAI 1-6, thermal construcation ophysics, calculation of thermal bridges, sound calculation and insulation, room acoustics
Client: |
OFB Hr. Kunz |
Cost: |
3 Mio. € |
Conversion of a heart surgery hospital into the new local health authority of Frankfurt am Main
|
structural engineering HOAI 1-6, thermal construcation ophysics, calculation of thermal bridges, sound calculation and insulation, room acoustics
|
2007
21 Mio.
OFB Frankfurt Hr. Berg
Client: |
OFB Frankfurt Hr. Berg |
Cost: |
21 Mio. € |
New construction of a regional data processing centre combined with offices
|
|
2007
56 Mio.
OFB Frankfurt Hr. Berg
Client: |
OFB Frankfurt Hr. Berg |
Cost: |
56 Mio. € |
New constrcution of an school campus
|
|
2007
Stadtwerke Hanau Hr. Neumeier
Client: |
Stadtwerke Hanau Hr. Neumeier |
Cost: |
€ |
New construction of an appartment building with combined heat and power station
|
|
Client: |
Wohnheim |
Cost: |
€ |
Refurbishment of an appartment building
|
|